Trivandrum Port · Vizhinjam · TRV
How is Trivandrum Port performing?
India’s first deepwater transshipment port opened to commercial traffic in December 2024. Since July 2024 it has handled 26,56,461 containers (TEU) in 1,195 ship calls. In October 2026 it handled 1,48,706 TEU, its best month so far.
Updated 5 November 2026
How much cargo does it handle?
Monthly volume has more than doubled since commercial operations began, from 70,638 TEU in December 2024 to 1,48,706 TEU in October 2026.
Is it handling more ships, or more cargo per ship?
Mostly more cargo per ship. Calls stayed between 39 and 62 a month in 2026. TEU per call stayed between 1,675 and 2,447 from January 2025 to July 2026, then passed 3,000 in September and October.
Ship calls per month
TEU per ship call
TEU per call is monthly TEU divided by ship calls. Early months with very few calls are left out of the second chart.
How does that compare with the plan?
Phase 2 is meant to raise capacity to 5.7 million TEU by December 2028. Here is where cargo stands today.
- Last 12 months, to October 2026
- 14,46,321 TEU
- First full financial year, 2025–26
- 12,96,743 TEU
- Passed 2 million TEU in total
- May 2026, reported as the fastest Indian port to do so
- Phase 2 capacity target
- 5.7 million TEU by December 2028
Capacity is what the port can handle. Throughput is what it does handle. They are not the same measure.
What is being built around it?
A port earns the most when roads, rail and nearby ports and industry are built around it. Different agencies plan and fund each piece. Figures are as reported.
- Cargo out
- A 10.7 km rail link from Vizhinjam to Balaramapuram, with a 9.43 km tunnel. Target December 2028. Land acquisition is the main constraint. An Outer Ring Road to Navaikulam is also proposed.
- Kollam
- A 101 m Sagarmala berth at Kollam port, and the Neendakara fishing harbour.
- Kochi
- Cochin Port and the Vallarpadam terminal, Cochin Shipyard, a planned ship repair facility and a proposed ship-block facility.
- Beypore and Azhikkal
- Draft improvement planned at Beypore. Azhikkal is planned as a greenfield port.
- Inland waterways
- National Waterway 3 from Kollam to Kottapuram is largely unused. Full operation is targeted by 2028.
What can you do with this?
- Route calculator →
Importing or exporting?
Check transit times from Trivandrum to your port.
- Our services →
Planning a project or investment?
We analyse port data and advise on projects around the port.
- Subscribe →
Following the port?
Weekly coverage, every Monday.
Monthly data, July 2024 to October 2026
| Month | Ship calls | TEU | TEU per call |
|---|---|---|---|
| Jul 24 | 3 | 6,862 | 2,287 |
| Aug 24 | 0 | 0 | – |
| Sep 24 | 12 | 48,586 | 4,049 |
| Oct 24 | 23 | 30,784 | 1,338 |
| Nov 24 | 30 | 58,288 | 1,943 |
| Dec 24 | 36 | 70,638 | 1,962 |
| Jan 25 | 45 | 85,635 | 1,903 |
| Feb 25 | 40 | 78,833 | 1,971 |
| Mar 25 | 51 | 1,08,770 | 2,133 |
| Apr 25 | 45 | 1,04,413 | 2,320 |
| May 25 | 49 | 1,14,432 | 2,335 |
| Jun 25 | 43 | 99,976 | 2,325 |
| Jul 25 | 43 | 1,05,228 | 2,447 |
| Aug 25 | 49 | 1,18,943 | 2,427 |
| Sep 25 | 40 | 86,225 | 2,156 |
| Oct 25 | 49 | 92,527 | 1,888 |
| Nov 25 | 53 | 1,03,471 | 1,952 |
| Dec 25 | 57 | 1,21,234 | 2,127 |
| Jan 26 | 62 | 1,23,092 | 1,985 |
| Feb 26 | 54 | 1,08,524 | 2,010 |
| Mar 26 | 59 | 1,18,678 | 2,011 |
| Apr 26 | 61 | 1,02,203 | 1,675 |
| May 26 | 56 | 1,30,863 | 2,337 |
| Jun 26 | 47 | 1,13,292 | 2,410 |
| Jul 26 | 49 | 1,04,448 | 2,132 |
| Aug 26 | 51 | 1,41,759 | 2,780 |
| Sep 26 | 39 | 1,30,051 | 3,335 |
| Oct 26 | 49 | 1,48,706 | 3,035 |
Sources: the port’s monthly summary supplied to Motherport News; Motherport News weekly reports; Maritime Gateway; The Week; India Sea Trade News; Keralakaumudi. Where sources differ, we use the latest. We confirm project figures with the owning agencies during any assignment.